Scope clarity → split rate reference
Well-defined (spec'd)1.0-1.2×
Requirements written · acceptance criteria defined · designs approved · tech approach agreed
Mostly defined1.2-1.5×
Most requirements written · some open questions · rough designs exist · 1-2 tech spikes expected
Exploratory1.5-2.0×
High-level description only · active discovery ongoing · multiple technical unknowns
Very unclear2.0-3.0×
Concept only · no written requirements · R&D phase · scope could change radically
80%
Factor Weeks Prob
◎
Ready to forecast
Configure your inputs and run the simulation to generate a probabilistic delivery forecast.